Update from Steve Lorentzen: Administrative Services Bureau of Court Facilities
Laconia District Court
There is still plenty going on inside. The outside pictures show the new vestibule area with a new, sliding, front entry door. You can also see that the grading has begun and the beginning of front stairs that will come to a nice block landing in front of the front entry. Ramps are on both sides of the building with the handicap accessible ramp on the right side. All of the brick re-pointing, exterior window trim, slate roof repair, and painting are complete. The only exterior building detail left are the two chimney caps. The grass, trees, and top coat of the asphalt will all be done this coming spring 2009. As of this writing, we are still planning a mid-January move-in based on the contractor's latest completion date.
|